Project Update: April 15, 2025
What's Going On
We are excited to share the latest updates on our progress at the NC A&T campus!
Details
Brick Veneer
Brick veneer in progress in the courtyard and on the exterior of the West building.
Air Barrier
Air barrier at 90% completion
Windows
Window installation at 75% completion. Curtain wall 1 installation in progress.
MEP Trades
MEP trades complete on the 1st, 2nd, and 3rd floor of the West and 1st and 2nd floor of the East. In progress on the 4th floor of the West and 3rd floor of the East.
Drywall
Drywall complete on the 1st floor of the West. In progress on the 2nd and 3rd floor of the West.